WWZ Zug Commercial Building

This new office building is being designed to meet high standards for energy efficiency for WSP’s client WWZ Zug, a Swiss supplier of energy, telecommunications and water.


Location

  • Zug, Switzerland

Client

  • WWZ Energie AG, Zug

Project Value

  • CHF 7 Million

Project Status

  • Due to be completed end of February 2021

Architect

  • Boltshauser Architekten AG

General Planner

  • S+B Baumanagement AG

The new WWZ Zug building is an office building with a built-in data centre. The building is made up of three upper floors for office use and three basement floors for parking. The data centre, emergency generator and transformer equipment are on the first basement floor. The roof and facades are fitted with photovoltaic panels.

The data centre meets the Uptime-Institute "Tier II Standard," and the installed cooling capacity is 2 x 566 kW.

As part of the project, we will design the following installations: 

  • Heating 
    Heat is generated by two heat pumps, each consisting of two 70 kW modules. The waste heat from the data centre is purified and then fed into the heating network.

  • Cooling 
    Two cooling units, each consisting of an ammonia chiller with a 560-kW piston compressor.

  • Warm Air/Cold Air Distribution 
    Air conditioning of the offices on floors 0 to 2 with multifunctional hybrid ceiling modules for heating, cooling, ventilation and acoustics.

Image courtesy of: Architektur und Visualisierung Boltshauser Architekten AG