WSP was retained by Global Sustainable Electricity Partnership (GSEP) to conduct a feasibility study for introducing electrified urban public transit via battery electric buses (BEBs) in Lima, Peru.


Location

  • Lima, Peru

Sector

  • Rail and Transit
  • Power Generation and Delivery
  • Bus Rapid Transit
  • (View all)

Service

  • Advisory Services
  • Asset Management
  • Quality Assurance
  • (View all)

Client

  • Global Sustainable Electricity Partnership

Project Status

  • Phase 1: Feasibility Study - Started July 2017, Completed October 2017. Phase 2: Vehicle Specification & Inspection (in progress)


Feasibility Study

The project objective is to study the feasibility of fully incorporating a BEB into a public transit line, preferably on a bus route with a high percentage of student clientele requiring transport between downtown Lima and the University of Lima campus.

Client Brief/Project Challenges

WSP provided the following services as a part of the feasibility study: 

  • Transit Route Service Assessment for the introduction of electric buses 
  • Addressing the challenge of evaluating electric buses in a new market, including operating conditions of passengers, stops, elevations and vehicle schematics. 
  • Vehicle Configuration and Recommendations for electric buses to suit route needs/requirements, utilizing the Battery Optimization and Lifecycle Tool (BOLT) to determine the feasibility of operating BEBs
  • BEB Vehicle Specification Development and Production Quality assurance oversight
  • Facility and Charging Infrastructure (end point) Assessment and Feasibility of installation at identified site locations. 
  • Operations & Maintenance Impact Assessment of electric buses in Peru; identifications of gaps to be addressed for managing new technology 
  • Environmental Impact Assessment, including GHG reductions 
  • Total Lifecycle Cost Model of electric buses 
  • User Experience Analysis 
  • Pilot Project Strategy, including recommendation of an optimal route for the pilot
 

Our Approach

WSP analyzed and evaluated the potential for piloting electric buses using its proprietary simulation Battery Optimization and Lifecycle Tool (BOLT). Furthermore, WSP developed a Total Lifecycle Cost for electric buses. 

Outcome/Client Benefits

WSP recommended the route to be selected for an electric bus pilot program, and identified other options, including BRT electrification and an 18m bus option. WSP developed the methodology for the management and monitoring of the pilot and provided insight on supporting a greater public awareness of the advantages of clean energy and access to a new technology for the Lima transportation system. WSP performed the following:

  • Electric Bus Feasibility Study Development 
  • Pilot Program Development and Recommendation

List of primary services

  • Electric bus system selection
  • Electric charging options sift
  • Whole-life cycle cost comparisons and business case
  • Feasibility study
  • Development of electric bus pilot program and rollout strategy 
  • Pilot project route selection

Innovations

  • Electric bus lifecycle cost
  • Electric bus performance and transit route modelling
  • Electric bus maintenance program
  • Electric bus plant production quality inspection