The project was required to pass urban design review process to comply with local regulations. WSP assisted the design team in reviewing and integrating regulation requirements to fulfil design expectations.
The project is situated above the restricted area of Taipei Metro and High-Speed Rail tunnel, so the project has to make any possible displacement of the tunnel must be detected and monitored during the entire construction period.
Tailored flat slab construction
To maximise the clearance of the basement for parking and retail spaces, flat slabs with thickness of 30cm were designed. Thus, the forming and shoring systems were carefully monitored due to thicker slabs and heavier concretes, as well as the timing for dismantling the shoring system.
With its outstanding quality of design and work, the project has been well recognised by a number of awards, including the Special Award in Commercial Building Planning and Design Category at the prestigious FIABCI-Taiwan Real Estate Excellence Awards in 2020.