Collaboration
WSP worked in an ECI type arrangement with Downer, with no formal contractual linkages. A number of mechanisms supported close collaboration between DCC, WSP and Downer, including weekly project meetings (to discuss programme and project risks), Design & Project Risk Workshops, Safety by Design Workshops and Construction Review Workshops.
This close collaboration, along with a holistic approach to risk management, supported the de-risking of what was a highly complex construction project affecting multiple businesses in the CBD. We carefully managed the project scope and were awarded subsequent design stages of the project.
There was a significant change, eight weeks from delivery when we stopped work on Option 1 and commenced Option 2 (due to unforeseen landowner delays). This was a massive change for the team, however despite this, we delivered to a tight programme and under budget (approx. 3% of the agreed WSP fee was not charged to the client - in the region of $65K).
Due to WSP’s rigorous management of project risk, the client was protected from unforeseen project costs (e.g. building damage/construction delays).
There were high levels of client satisfaction with this project, which was extremely high risk for the client and carefully managed around costs and potential delays