To ensure the mechanical integrity of the terminal’s tanks and piping, we supported hydrotest permitting by evaluating regulatory requirements and preparing discharge plans. Our team conducted sampling of the hydrotest water source and coordinated notifications to TCEQ and other agencies. We conducted Clean Water Act permitting and wetland delineations, ensuring compliance with federal and state water quality standards.
In anticipation of future crude oil storage, we prepared an EPA Wastewater Discharge Permit application for hydrotest water discharges. We secured temporary and permanent water use permits for withdrawals from the Houston Ship Channel, which granted rights for hydrostatic and fire system test water use.
Integrated environmental services
Throughout the development of the Gulf Coast Marine Terminal, our team delivered a full suite of environmental services tailored to meet regulatory requirements and support the client’s operational goals.
We prepared emissions inventories, evaluated control technologies and completed Title V and nonattainment New Source Review permitting to help the project meet stringent air quality regulations in the Houston area.
We also developed and implemented a Stormwater Pollution Prevention Plan, provided waste characterization services and evaluated water source alternatives to support hydrotest and fire system testing. These efforts ensured all environmental aspects of the project were addressed with precision and efficiency.