YEARS AHEAD OF SCHEDULE
20+
IN SAVINGS
$10M+
REGION PROTECTED
174mi² 

Location

  • Illinois, USA
Img-Website-Southwestern-Illinois-1200x1000-1

How levees work and the challenge of seepage

Levees are engineered embankments designed to protect low-lying areas from flooding by acting as barriers that contain rising water levels. They are typically constructed from compacted soil, clay, or engineered materials and are reinforced with drainage structures, such as relief wells and seepage berms, to manage water pressure and prevent failure.

One of the greatest challenges levees face is seepage, which occurs when water infiltrates the levee system, potentially weakening its integrity. Seepage can manifest in two critical ways:

  • Through-seepage happens when water moves horizontally through the levee, eroding material and potentially causing internal instability.
  • Underseepage occurs when water flows beneath the levee through permeable soil layers, creating pressure that can lead to sand boils—a sign of potential levee failure.

If left unaddressed, excessive seepage can compromise levee stability, leading to erosion, structural weakening, or even catastrophic breaches. Effective flood protection requires careful engineering solutions, such as relief wells, seepage berms, and cutoff walls, to control water movement and maintain levee integrity.

Img-Website-Southwestern-Illinois-414x496

Geotechnical and structural assessments

We conducted extensive subsurface investigations, including soil borings and geotechnical testing, to evaluate foundation stability and seepage risks. This data informed critical decisions about underseepage mitigation, relief well placement, and the design of seepage berms. Structural assessments of levee components, such as floodwalls, culverts, and closure structures, ensured they met modern safety standards.

Seepage and stability improvements

A major focus of our work was addressing underseepage and through-seepage risks. The team designed and optimized relief wells to improve drainage efficiency while minimizing new construction costs. They also implemented hybrid seepage solutions, integrating existing relief wells with strategically placed seepage berms to enhance performance while reducing material and excavation costs.

Hydraulic and hydrologic modeling

We performed detailed hydraulic and hydrologic studies to assess floodplain impacts, internal drainage conditions, and rainfall severity. This included modeling how water would move through the levee system under extreme flood conditions and optimizing pump station capacity and drainage structures to handle prolonged flood events.

Value engineering and cost optimization

To ensure project affordability without compromising safety, we applied advanced 3D modeling techniques to refine construction plans, minimizing unnecessary excavation and material use. By leveraging existing infrastructure wherever possible, we helped the FPD Council significantly reduce project costs while still achieving the necessary improvements.

Construction support and quality assurance

We also provided oversight and technical support throughout construction, ensuring work adhered to FEMA and USACE standards. We assisted with contractor coordination, material testing, and compliance verification to ensure that every upgrade met rigorous flood protection requirements.

Img-Website-Southwestern-Illinois-1200x1000-2

Impacts on the community

  1. Economic and financial stability: The project prevented a potential catastrophe that would have had dire economic and financial consequences for businesses and residents. By securing FEMA accreditation for the levee systems, the project avoided skyrocketing flood insurance premiums, plummeting property values, and costly new building regulations.
  2. Protection of critical infrastructure: The levees safeguard a 174-square-mile region of immense economic and historical significance, including major manufacturing facilities, extensive multimodal transportation infrastructure, and the Cahokia Mounds, a UNESCO World Heritage Site. The successful rehabilitation of the levees ensured the protection of these critical assets.
  3. Community safety: The project addressed the risk of catastrophic flooding, which could have caused damage estimates in the tens of billions and threatened the stability and prosperity of the entire region. By enhancing flood resilience, the project provided essential protection to the community.
  4. Cost efficiency and timeliness: The project was completed ahead of schedule and under budget, with a total construction cost of approximately $75 million—far below early estimates in the hundreds of millions. This achievement not only safeguarded critical infrastructure but also restored confidence in the region’s flood defenses.
  5. Successful performance during flood events: The levee improvements were put to the test during the historic flood of 2019, and they performed exactly as intended, preventing what could have been a catastrophic outcome. This demonstrated the effectiveness of the project in providing critical, time-sensitive protection to the community.