The suite of four wind farms spans nearly 120,000 acres across three New Mexico counties and generates 1,050-MW of wind energy — enough annual electricity production to support 900,000 people. The project delivers this electricity to the state’s grid and broader Western markets, including California.
In addition to the wind farms, the project involved construction of a 155-mile-long, 345-kV transmission line and two substations. The Western Spirit Switchyard (WESP) serves as the point of interconnection for the four windfarms, and the Abo Series Compensation Station regulates the line’s power flow.
Pattern engaged our team as owner’s engineer to provide preliminary line and station design, estimating and permitting support. We also designed the Supervisory Control and Data Acquisition (SCADA) for all four wind farms as well as the transmission system, and we were responsible for SCADA planning and coordination with Public Service of New Mexico.
Finally, we designed and coordinated a detailed energization plan, including commissioning support.