The Kensington Building
WSP worked with Ashby Capital and Janson Urban to reuse and grow the existing structure which created larger more effective retail and office spaces while reducing carbon emissions from construction.
Location
- London, United Kingdom
Project Status
- Complete
Existing structure reused
>60%
Increase in overall gross area
~45%
Below 2020 LETI embodied carbo target for structure
44%
Image on the left shows the parts of the building that were demolished in red and the image on the right shows the new structure in blue.
The areas in blue show where we incorporated the new structure. The left image is of the foundations and shows where we retained the existing foundations. The right image shows the combination of new and existing structure of a typical floor area.
With the built environment contributing about 40% of the UK’s carbon footprint, it’s imperative that investors and developers look beyond the operational carbon footprint of their buildings to the emissions produced in the construction process and embodied carbon. Working with WSP to reuse and repurpose as much of the previous building as possible, we have reduced embodied carbon at The Kensington Building by 30% compared to a typical new-build office, proving that the construction of new office buildings doesn’t have to be environmentally damaging.