In Aotearoa's previous rounds of PPPs, the same standard agreement with only minor adjustments was applied across different asset classes, including prisons, schools, and roads. This was a mistake. Flexibility is crucial. Each project should have a tailored procurement approach and adaptable procurement model.
‘Progressive PPPs’, a model developed in North America, are another way of being smarter around risk allocation. These feature an early collaborative stage (similar to the Early Contractor Involvement (ECI) model used in Aotearoa) – where the private partner is engaged early in the project based on their qualifications and experience, rather than price.
Progressive PPPs let private partners provide input earlier in the project development process, addressing issues like route alignment (in horizontal projects such as roads), consentability, and the availability of materials. The process is iterative and collaborative, which leads to a more informed understanding of risks before converting into a fixed-price PPP contract.
Making sufficient preliminary site investigations and reports available to private sector bidders is another part of the solution. If the Government wants to run competitive PPP bids, providing information in advance about known risks in a form that bidders can rely on will help better price in risk.
Exploring shared risk
The purist view of PPP risk allocation is often very black and white. It either sits with the public sector, or the private sector. But there’s a third way – shared risk.
A nice example can be found with the Tłı̨chǫ Highway - a 100-kilometre all-weather gravel road in northern Canada connecting a remote First Nations community to the Yellowknife Highway.
Built on permafrost, the ground stays frozen year-round. Building on either permafrost or non-permafrost ground is relatively straightforward but designing for potential climate change impacts on a permafrost road proved tricky.
The Government of the Northwest Territories (GNWT) in Canada wanted a fixed-price contract for designing, building, and maintaining the road for 25 years, but factoring in climate change risk made it expensive.
A risk-sharing plan was created. The private sector partner designed for likely, scientifically modelled climate outcomes. Opened in 2021, if the climate outcomes turn out worse than modelled, they'll cover extra costs up to a limit, with GNWT covering the rest. This way, the private partner had an incentive to manage risks without overpricing for worst-case scenarios.
Success is about smart risk management, not wild risk taking. That’s true of infrastructure PPPs, and it's true of life. For Aotearoa, getting the best out of PPPs means moving past highly standardised contracts and adopting flexible risk allocation practices that will, in the long run, benefit the country and its critical infrastructure needs.